Construction Update

878 España

10-01-2018



878 España Construction Updates as of Q3 2018

(1)  On-going Interior Fit Out Works - Ground Floor (2) On-going Completion of Residential Units and Amenities - 6th Floor

(3-4) On-going Functionality Test - 7th & 8th Floor (5-6) Units ready for Functionality Test - 7th to 15th Floors

(7-8) On-going Punchlisting of Units - 16th to 20th Floors (9) On-going Painting - 21st Floor

(10) On-going Painting and Installation of Vinyl - 22nd Floor (11) On-going Painting and Installation of Ceiling - 23rd Floor

(12-13) On-going Painting Works - 24th to 29th Floors (14) On-)going Painting Works and Waterproofing - 30th & 31st Floors

(15) Ready for Painting Works - 33rd & 34th Floors (16) On-going Plastering - 35th to 37th Floors.

CONTACT US

FILL-IN THE FORM AND FIND OUT ABOUT OUR LATEST PROJECTS AND PROMOS

OFFICE ADDRESS

UGF Worldwide Corporate Center, Shaw Boulevard,
Mandaluyong City, Philippines 1552

TELEPHONE NUMBERS

Landline: (+632) 650-0753
Mobile: (+63) 999 887-1705

EMAIL ADDRESSES

info@vistaresidences.com.ph

ONLINE INQUIRY